2018

Project Started

Feb ,2018(3%)
  •  Mobilization 100%
  •  Site clearing 100%
  •  Piling 40%
  •  Overall progress 3%
Mar ,2018(8%)
  • Mobilization  100%
  • Site hoarding 100%
  • Site fencing  100%
  • Site office  100%
  • Piling  85%
  • Overall progress  8%
April ,2018 (12%)
Mobilization 100%
Site hoarding 100%
Site fencing 100%
Site office 100%
Piling 100%
Sheet pile 100%
Overall progress 12% 
May ,2018 (16%)
  • Mobilization 100%
  • Site preparation 100%
  • Piling & Sheet pile 100%
  • Soil protection 50%
  • Overall progress 16%
June ,2018 (18%)
  • Soil protection 80%
  • Overall progress 18%
July ,2018 (21%)
• Soil Protection 95%
• Foundation 80%
• Overall Progress 21%
August ,2018 (26%)
• Soil Protection 95%
• Foundation  90%
• ฺBasement    31%
• Overall Progress 26%
September ,2018 (30%)
• Soil Protection 95%
• Foundation  100%
• ฺBasement    52%
• Overall Progress 30%
October ,2018 (33%)
• Soil Protection 95%
• Foundation  100%
• ฺBasement    60%
• Overall Progress 33%
33%

OF OVERALL PROGRESS

As of October, 2018